News APP

NewsApp (Free)

Read news as it happens
Download NewsApp

Available on  gplay

This article was first published 8 years ago
Home  » Sports » Unfinished velodrome main concern 100 days from Olympics

Unfinished velodrome main concern 100 days from Olympics

April 27, 2016 20:56 IST
Get Rediff News in your Inbox:

- 'The biggest problem, the biggest challenge and the job that gave us most problems and missed the deadline was the velodrome.'

IMAGE: An aerial view of the 2016 Rio Olympic park in Rio de Janeiro, on April 25, 2016. With 100 days to go before the Olympic games begin in Rio de Janeiro, hosts Brazil famous for doing things at the last minute face a novel situation -- the organisation is not an issue, political turmoil and apathy are. Photograph: Ricardo Moraes/Reuters

The unfinished cycling arena is the biggest issue facing the Rio de Janeiro Olympics 100 days before the games begin, the city's mayor said on Wednesday.

The velodrome is only 85 percent ready and workers need another 30 to 40 days to finish the structure, meaning there will not be time for a proper test event before the games begin on August 5.

"The biggest problem, the biggest challenge and the job that gave us most problems and missed the deadline was the velodrome," Mayor Eduardo Paes told reporters in Rio. "The track is practically done. We have 30 to 40 more days of intense work but we are on schedule."

Rio's original plan was to use the velodrome built for the 2007 Pan American Games but that was scuppered after officials said the venue did not meet Olympic standards.

The old one was dismantled for rebuilding in the centre of Brazil and a brand new one erected in Rio's Olympic Park, the main cluster of venues.

Paes, who declared the park open on April 12, said it is 98 percent complete with the tennis centre needing last-minute work. The main courts are ready but temporary seating still needs to be installed, he said.

Paes also announced public holidays on three days during the games, both for the opening and closing ceremonies and on August 18, the day of the men's triathlon event in Copacabana.

Following a strategy used during the 2014 World Cup, officials hope to reduce the amount of traffic by keeping cars off the road and through the use of special traffic lanes for Olympics visitors.

Paes said 260 kilometers (161 miles) of traffic lanes will be used to facilitate the movement of athletes and officials. The lanes will be opened for tests on July 25 and be fully operational six days later.

Rio was last month declared the fourth most-congested city in the world by navigational device manufacturer TomTom.

"We are at the point many people doubted," Paes said. "But we are going well ... 100 days is always a landmark, it's a demanding period and there is a lot of pressure."

Get Rediff News in your Inbox:
Source: REUTERS
© Copyright 2024 Reuters Limited. All rights reserved. Republication or redistribution of Reuters content, including by framing or similar means, is expressly prohibited without the prior written consent of Reuters. Reuters shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

New Zealand's tour of India 2024

New Zealand's Tour Of India, 2024