News APP

NewsApp (Free)

Read news as it happens
Download NewsApp

Available on  gplay

This article was first published 6 years ago
Home  » News » Will defence ministry okay Anil Ambani's Reliance Naval?

Will defence ministry okay Anil Ambani's Reliance Naval?

By Ajai Shukla
September 28, 2018 10:45 IST
Get Rediff News in your Inbox:

Warship building projects worth at least Rs 630 billion have ground to a standstill.
The defence ministry has halted tendering in wait for a government decision on whether to allow, or to exclude, Anil Ambani's shipbuilding firm from those contracts.
Ajai Shukla reports.

On Wednesday, September 26, the defence ministry announced a contract for building two diving support vessels awarded to the defence public sector undertaking, Hindustan Shipyard for an estimated Rs 20 billion.

Obscured by the fanfare around this relatively small order, warship building projects worth at least Rs 630 billion have ground to a standstill.

In all these cases, the defence ministry has halted tendering in wait for a government decision on whether to allow, or to exclude, Anil Ambani's shipbuilding firm -- Reliance Naval and Engineering -- from those contracts.

 

The navy has a major grouse with RNAVAL, which has failed to deliver five naval offshore patrol vessels, an order that Pipavav Shipyard won in 2001. It was to deliver the first NOPV in November 2014 and all five before November 2016.

But, four years after the delivery date, not even the first NOPV has been handed over.

"For a similar infringement, the navy cancelled an order on ABG Shipyard, leading to its bankruptcy," points out a shipbuilding industry executive.

The defence ministry is also undecided on allowing RNAVAL to bid in warship tenders because IDBI Bank -- one of its biggest lenders -- has taken RNAVAL to the National Company Law Tribunal, seeking debt resolution.

An 18-member consortium of lenders has reportedly declined RNAVAL's settlement offer for at least Rs 90 billion in outstanding loans. NCLT is understood to have granted time till October 10 for resolution.

At least one lender -- Vijaya Bank -- has classified its loan to RNAVAL as a non-performing asset. The company's auditors, Pathak HD & Associates, have noted that cash losses, erosion of net worth, recalled loans, and other adverse indicators 'may cast significant doubt on the company’s ability to continue as a going concern'.

In the circumstances, RNAVAL's presence has stalled a tender, worth an estimated Rs 200 billion, for building four landing platform docks in India -- large vessels that carry helicopters, tanks, and vehicles for amphibious landings, or for disaster relief.

In 2014, the navy issued a request for proposal to three private shipyards: Larsen & Toubro, ABG and Reliance's Pipavav shipyard, later renamed RNAVAL. The winner was to build two LPDs, with HSL nominated to build the other two.

However, with ABG going bankrupt, a fresh RFP was issued in May 2017 to L&T and RNAVAL for building all four LPDs.

Since then, action has stalled on whether RNAVAL is eligible. The bids still remain unopened.

"The LPD provides us an important capability. It will take minimum two years from RFP to contract signature and another three years to build the LPDs. So 2023 is the earliest we can get this capability," says a senior admiral.

Worse, at least 42 vessels, urgently needed by the navy and coast guard, are facing similar or longer delays because the final list of eligible bidders is not finalised.

There are no questions over the eligibility of the four DPSU shipyards -- Mazagon Dock, Mumbai; Garden Reach Shipbuilders & Engineers, Kolkata; Goa Shipyard, and HSL -- and private shipbuilder L&T has demonstrated both engineering capability and shipyard capacity.

However, one question is holding up the tendering: Is RNAVAL also eligible, given its building record and financial condition?

Sources in the navy say the 42 vessels lined up for tendering are: Seven next-generation corvettes, six next-generation missile vessels, six next-generation OPVs, four multi-purpose support ships, three cadet training ships, five survey vessels, and one survey training vessel.

The coast guard is waiting to tender two pollution control vessels and eight fast patrol vessels.

Industry sources say the total value of the navy's contracts would be at least Rs 600 billion.

The coast guard vessels would require another Rs 30 billion.

Finally, the decision on RNAVAL's eligibility will be crucial for the execution of Project 75(I), to build six conventional submarines in India.

The government is working on guidelines for choosing 'strategic partners' for submarine building, based on technology transferred by a chosen foreign vendor.

The defence ministry and Reliance Defence did not respond to requests for comments on these issues.

On Tuesday, September 25, after clearing changes to the Defence Procurement Procedure, the defence ministry stated: 'These measures will go a long way in obviating procedural delays and will hasten activities, besides shrinking the procurement timelines giving due preference to indigenisation.'

However, private shipyards that have invested heavily in creating capacity for warship building, say their financial viability depends upon whether the order bottleneck can be resolved quickly.

Central to that is a decision on RNAVAL's eligibility.

Get Rediff News in your Inbox:
Ajai Shukla
Source: source