Despite the government’s efforts to fast-track large projects by constituting the Cabinet Committee on Investment, the proportion of mega projects (Rs 1,000 crore or more) facing delays has risen, according to data from the ministry of statistics and programme implementation.
According to the latest data, until May, 48.3 per cent of the total 207 projects worth Rs 1,000 crore (Rs 10 billion) or above, also termed as mega projects, faced delays and witnessed a cost overrun of 19.2 per cent from the originally-sanctioned Rs 656,000 to Rs 781,000.
In April, around 47 per cent projects were running late and the cost exceeded by 18.3 per cent.
During May, three projects - two from the power sector and one from fertiliser -- reported completion.
In the month, 11 projects were delayed additionally from that in the previous month.
As a result, the proportion of projects on schedule rose marginally from 32.5 per cent in April to 32.8 per cent in May. Some projects did not have commissioning deadlines.
According to MoSPI, among the reasons for the delay included that of land acquisition, forest clearance, award of works, legal issues, seepage in power house, etc.
The government set up CCI in the last financial year to fast-track projects that were stuck. However, according to experts, nothing seemed to be working on the ground level as a major chunk of projects still faced delays.
Finance Minister P Chidambaram said in a written reply to Rajya Sabha that on August 1, 2013, 167 projects entailing an investment of Rs 6.57 lakh crore (Rs 6.57 trillion)